Share February 2023 Construction Update on Facebook
Share February 2023 Construction Update on Linkedin
Email February 2023 Construction Update link
The environmental restoration is complete. This is the final stage of the project and included planting native vegetation on the banks of the Chase River.
The facility is running well and this major refit has extended the life of this facility to serve our community reliably for many decades.
Thanks to our contractors, suppliers, engineers, and operating staff for completing this work safely and efficiently while managing flow through a temporary pumping system without any environmental incidents.
Share September 23, 2022 Construction Update on Facebook
Share September 23, 2022 Construction Update on Linkedin
Email September 23, 2022 Construction Update link
Construction of the pump station upgrade portion of this project is substantially complete. All the process piping within the pump station has been replaced, a new motor and process control system has been installed, and the works are operational. This upgrade will significantly extend the operating life of this critical infrastructure.
Share June 17, 2022 Construction Update on Facebook
Share June 17, 2022 Construction Update on Linkedin
Email June 17, 2022 Construction Update link
We are getting ready to renovate the pumping and electrical systems. Most of the construction will occur during July and August and have little impact on the public.
The final work on this project will take place in fall 2022 outside of the bird-nesting window. At that time, we will remove invasive plants and revegetate disturbed areas.
Share July 16, 2021 Construction Update on Facebook
Share July 16, 2021 Construction Update on Linkedin
Email July 16, 2021 Construction Update link
Construction is scheduled to return to the Chase River Pump Station in August for the installation of piping associated with the new valve station.
Access through the Pump Station Property to Chase River Estuary Park could be restricted at times, the park can still be accessed from the Northern side of the Chase River.
Share October 21, 2020 Construction Update on Facebook
Share October 21, 2020 Construction Update on Linkedin
Email October 21, 2020 Construction Update link
The City of Nanaimo water mains and pavement upgrades along Haliburton were completed in May 2020. Engineering of the pump station upgrade to replace corroded piping and steel platforms and an electrical and controls upgrade is well advanced. A development permit is required for this work due to the proximity to the Chase River. This project has been placed on hold pending the outcome of the permit application. Construction is expected to take place in the summer of 2021.
Share December 5, 2019 Construction Update on Facebook
Share December 5, 2019 Construction Update on Linkedin
Email December 5, 2019 Construction Update link
The
replacement of the wastewater forcemain along Haliburton Street is complete and
the pipeline is operational. This new pipeline will take substantial pressure
off the wastewater system with the additional capacity that it provides.
Work on the
overall project is only 50% complete but the project will be taking a break
over the Holiday Season and will start back up again in early January 2020.
The work
scheduled for January until the end of May 2020 will include the replacement of
the ageing City of Nanaimo water mains and the upgrade of the pavement surface
along Haliburton street within the project area. Additional Upgrade work around
and inside the Chase River Pump Station will continue till late summer 2020,
but this work will have minimal impact on the public.
The
temporary road surface will be in place and maintained by Milestone Contracting
until the weather warms up to allow for the final pavement upgrade.
The
Regional District of Nanaimo and the City of Nanaimo would like to thank you
for your patience through this important project and wish you all a wonderful
Holiday Season.
Share Road Closure and Transit Service Alert on Facebook
Share Road Closure and Transit Service Alert on Linkedin
Email Road Closure and Transit Service Alert link
Please be advised that periodic interruptions to road traffic may occur from September 3, 2019 to May 31, 2020. During this time, BC Transit services will be re-routed. For details on the Transit Plan, please refer to the August 13, 2019 Construction Notice (page 2).
Share Construction begins September 3, 2019 on Facebook
Share Construction begins September 3, 2019 on Linkedin
Email Construction begins September 3, 2019 link
Utility upgrades will occur from September 3, 2019 until May 31, 2020. Construction activities will occur between the hours of 7:00
AM and 7:00 PM Monday to Friday.
For questions or concerns, please call the contractor, Milestone
Equipment Contracting, at 1-888-484-7303.
Share Contract for Construction Services Awarded on Facebook
Share Contract for Construction Services Awarded on Linkedin
Email Contract for Construction Services Awarded link
At the Regular Board meeting on June 25, 2019, the RDN Board:
- awarded the Construction Services contract for the Chase River Pump Station and Haliburton Street Sanitary Sewer Forcemain Upgrade Project to Milestone Contracting Inc. for a total contract value of $2,987,730 (excl. GST).
- awarded the Construction Management contract to Jacobs Engineering for a value of $245,000.
- approved the addition of $1,285,257 to project budget which will be reimbursed by the City of Nanaimo through a cost-sharing agreement.