Share Construction is Complete! on Facebook
Share Construction is Complete! on Linkedin
Email Construction is Complete! link
The RDN is pleased to announce that construction on the Secondary Treatment Upgrade Project is complete. The $82 million upgrade is the largest capital expenditure in the RDN's history. See the news release for more information.
Also, watch the ribbon cutting and view the new video of the completed GNPCC Secondary Treatment Upgrade Project as well as new photos added to the photo gallery.
Share July 16, 2020 - Notice to Residents on Facebook
Share July 16, 2020 - Notice to Residents on Linkedin
Email July 16, 2020 - Notice to Residents link
Please read the Notice to Residents for more information on new frontage trail on Hammond Bay Road between McGuffie Road and Shores Drive.
Share July 9, 2020 - Notice to Residents on Facebook
Share July 9, 2020 - Notice to Residents on Linkedin
Email July 9, 2020 - Notice to Residents link
Please read the Notice to Residents for a project update and information on the construction of a new frontage trail on Hammond Bay Road between McGuffie Road and Shores Drive.
Share February 19, 2020 - Notice to Residents on Facebook
Share February 19, 2020 - Notice to Residents on Linkedin
Email February 19, 2020 - Notice to Residents link
The Contractor has obtained a Noise Bylaw Exemption for February 11 and February 19, 2020. See the Notices for more information.
Share Holiday Construction Expectations on Facebook
Share Holiday Construction Expectations on Linkedin
Email Holiday Construction Expectations link
The main construction works are expected to pause over the holidays from December 25, 2019 to January 1, 2020. During this time, construction support personnel will come and go to maintain systems. Construction will resume in the new year.
Share December 9, 2019 - Notice to Residents on Facebook
Share December 9, 2019 - Notice to Residents on Linkedin
Email December 9, 2019 - Notice to Residents link
The Contractor has obtained a Noise Bylaw Exemption for December 10 to December 12, 2019. See the Notice to Residents for more information.
Share December 2, 2019 - Construction Update on Facebook
Share December 2, 2019 - Construction Update on Linkedin
Email December 2, 2019 - Construction Update link
The project has achieved significant progress and is nearing completion. Construction and commissioning will continue into early 2020. Check out the Notice to Residents for a project update. Expectations for the coming months include:
- Noise - will remain similar as it has been through the fall. Intermittent noise will be generated to test new equipment, crush the last of the native rock, prepare the internal road, and backfill the secondary plant area.
- Truck traffic - will remain similar as it has been through the fall.
- Parking - construction crews will continue to park along McGuffie Road and Hammond Bay Road for the duration of the project.
- Odours - commissioning new systems may result in temporary strong odours.
- Late night or early morning work - the contractor will obtain City of Nanaimo Noise Bylaw Exemption Permits for any work required outside of noise bylaw hours.
Thank you for your continued patience as we complete this project. After the secondary treatment processes are successfully commissioned, GNPCC will produce substantially higher quality effluent and will reduce our impact on the environment.
Share November 26, 2019 – Upcoming Work Will Increase Project Noise on Facebook
Share November 26, 2019 – Upcoming Work Will Increase Project Noise on Linkedin
Email November 26, 2019 – Upcoming Work Will Increase Project Noise link
The Contractor will be crushing aggregate over the next month:
-
What to Expect - Activities will increase noise generated from the construction project, intermittently as required, for the duration of the time noted below. Noise associated with the aggregate crushing activities is expected to adhere to the City of Nanaimo Noise Bylaw
-
Dates - November 26 to December 21, 2019
-
Times - Monday through Saturday 7:30 a.m. to 6:00 p.m; Sunday 9:00 a.m. to 6:00 p.m.
Thank you for your continued patience as we complete this project.
Share Past Public Notices Available on Facebook
Share Past Public Notices Available on Linkedin
Email Past Public Notices Available link
Older Public Notices can still be found in the Notices section on the right bar.
Share March 9, 2018 – GNPCC Secondary Treatment Upgrade Project Receives $6 Million Federal Gas Tax Funds on Facebook
Share March 9, 2018 – GNPCC Secondary Treatment Upgrade Project Receives $6 Million Federal Gas Tax Funds on Linkedin
Email March 9, 2018 – GNPCC Secondary Treatment Upgrade Project Receives $6 Million Federal Gas Tax Funds link
The RDN has recently been approved for up to $6 Million
in funding from the Federal Gas Tax Fund to complete the GNPCC Secondary
Treatment Upgrade Project. Check out the News Release for more information.