What's Happening on Site: Spring 2024 Capital Project Update

The project team has been busy working on the following:

  • Key reviews of existing systems including the water system, sewer system, and utilities.
  • A required traffic impact assessment (TIA), the outcome of which will inform site planning going forward.
  • Drafting site plans which meet established bylaws.
  • Confirming the details of both the electrical ( i.e. connection options, timelines for required parts) and mechanical upgrades (i.e. sprinkler system, heating/cooling).

Construction will commence later this spring. The scope of work will include:

  • New roof with seismic and thermal upgrades
  • Hazmat remediation
  • Mechanical upgrades and improvements
  • Electrical upgrades
  • Site development for parking and access
  • Accessibility upgrades
  • Washroom upgrades to meet current codes
  • New exterior doors

Please continue to follow this page for updates. RDN Recreation staff will be onsite at the SWACA May 11th Plant Sale and look forward to answering any project questions you may have related to the building renovation plans. Park development planning (i.e. the grounds around the building) will begin later in2024

Share What's Happening on Site: Spring 2024 Capital Project Update on Facebook Share What's Happening on Site: Spring 2024 Capital Project Update on Twitter Share What's Happening on Site: Spring 2024 Capital Project Update on Linkedin Email What's Happening on Site: Spring 2024 Capital Project Update link