Construction Update

Work on the Village Way path project resumed on March 15th and substantial completion was achieved April 28, 2021.

Construction actives during this second phase of the project included the following tasks:

  • Completion of storm drainage works in preparation for paving
  • Completion of guard railings on retaining walls
  • Sawcut existing asphalt
  • Fine grade and preparation for paving
  • Road paving and curbing
  • Line painting
  • Pathway and driveway preparation and paving
  • Relocation of signage

The Path is open to the public as we work with our Contractor to rectify and wrap-up some minor deficiencies.

We have also identified some potential improvements that could enhance our final product and we are actively working through the details with our project stakeholders.

In general the RDN will be responsible to maintain the pathway portion of the trail and the Ministry will maintain the storm drainage systems, curbs, and everything road-side of the curbs.

Share Construction Update on Facebook Share Construction Update on Twitter Share Construction Update on Linkedin Email Construction Update link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>