Share Beach Access Update on Facebook
Share Beach Access Update on Linkedin
Email Beach Access Update link
The RDN is happy to announce that the beach access is now open.
The contractor has installed a temporary wooden railing at the beach access. There will be a short-duration closure to the beach access in the next couple of months to replace the wooden railing with a permanent metal railing.
Thank you for you continued patience while we complete the upgrade to the Bay Avenue Pump Station.
Share Construction Update on Facebook
Share Construction Update on Linkedin
Email Construction Update link
Paving is now complete. Installation of the site gate and fencing is underway. Due to unforeseen challenges experienced during commissioning, beach access via the new stairway is delayed. Access is now expected to be available by the end of May 2024.
Share Construction Update on Facebook
Share Construction Update on Linkedin
Email Construction Update link
Construction on the pumpstation is nearly complete.
- Final commissioning of the pump station is underway now.
- Paving and site restoration are scheduled for the spring.
- The beach access via the new stairway is expected to be available in mid-April 2024.
We appreciate your patience and understanding during this important upgrade.
Share Construction Update on Facebook
Share Construction Update on Linkedin
Email Construction Update link
Additional challenges onsite have delayed construction. Completion of the project is now expected by the end of November 2023. The RDN appreciates the continued cooperation and understanding of area residents while the pump station is upgraded to improve capacity and safety.
Share Construction Update on Facebook
Share Construction Update on Linkedin
Email Construction Update link
Continued delays on delivery of electrical and controls components have further extended the project timeline. Commissioning of the new wet well is postponed until May 2023. Completion of the project expected in August 2023. New photos are added to the gallery.
Share Construction Update on Facebook
Share Construction Update on Linkedin
Email Construction Update link
The project will reach a milestone in March when wastewater flows will be redirected to the expansion wet well and we will start operating with the new control system. This will allow the renovation of the existing wet well to begin.
We recognize that the temporary loss of the beach access is inconvenient. The beach access is expected to be available to the public by the end of June 2023. The size and location of the construction site makes the work difficult to complete quickly. This, combined with labour shortages and supply chain issues, have lengthened the timeline. Our contractors and engineers are working hard and construction is progressing steadily.
New photos are available in the gallery.
Share Construction Timeline Update on Facebook
Share Construction Timeline Update on Linkedin
Email Construction Timeline Update link
The construction timeline for this project is extended. Beach access will continue to be unavailable until the end of construction. Please follow the signs posted on site.
Share Construction begins July 19, 2021 on Facebook
Share Construction begins July 19, 2021 on Linkedin
Email Construction begins July 19, 2021 link
Construction on this project begins July 19, 2021 and will continue for about one year. Please note that public beach access from Bay Avenue will not be available during the construction period.
Share Contract for Construction Services Awarded on Facebook
Share Contract for Construction Services Awarded on Linkedin
Email Contract for Construction Services Awarded link
At the RDN Regular Board Meeting on May 25, 2021, the RDN Board awarded the construction contract to Coast Utility Contracting for $4,594,348.
Share Contract for Detailed Design Awarded on Facebook
Share Contract for Detailed Design Awarded on Linkedin
Email Contract for Detailed Design Awarded link
At the RDN Regular Board Meeting on October 22, 2019, the RDN Board awarded the contract for detailed design for the Bay Avenue Sewer Pump Station Upgrade to Koers & Associates Engineering for $454,847 (Motion 19-413).