July 16, 2021 Construction Update

Tree Clearing within the pipeline right-of-way off Meadow Lane is scheduled to start Monday, July 19, 2021. This is the start of the construction activity, followed by the delivery of piping material for the project. Excavation and pipeline installation is scheduled to start Monday, July 26, 2021 once the materials are delivered.

Share July 16, 2021 Construction Update on Facebook Share July 16, 2021 Construction Update on Twitter Share July 16, 2021 Construction Update on Linkedin Email July 16, 2021 Construction Update link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>