July 16, 2021 Construction Update

16 Jul 2021

Tree Clearing within the pipeline right-of-way off Meadow Lane is scheduled to start Monday, July 19, 2021. This is the start of the construction activity, followed by the delivery of piping material for the project. Excavation and pipeline installation is scheduled to start Monday, July 26, 2021 once the materials are delivered.