Departure Bay Forcemain Upgrade

Share Departure Bay Forcemain Upgrade on Facebook Share Departure Bay Forcemain Upgrade on Twitter Share Departure Bay Forcemain Upgrade on Linkedin Email Departure Bay Forcemain Upgrade link

Consultation has concluded

The Departure Bay Forcemain was constructed in 1974 and conveys wastewater from the Departure Bay Pump Station on Departure Bay Road to the Greater Nanaimo Pollution Control Centre on Hammond Bay Road. It carries wastewater from over half of the population in Nanaimo and is the largest of all forcemains operated by the RDN. A section near Meadow Lane Road, Kite Way, and Planta Road is corroded and must be replaced.

How you can get involved

To stay informed of project updates, please:

  • Register by clicking the "subscribe" tab on the right-hand side of the page. By registering you will be kept up-to-date with progress on this project through our electronic communication.
  • Check out the Project Map.
  • Explore this webpage to find out more.

The Departure Bay Forcemain was constructed in 1974 and conveys wastewater from the Departure Bay Pump Station on Departure Bay Road to the Greater Nanaimo Pollution Control Centre on Hammond Bay Road. It carries wastewater from over half of the population in Nanaimo and is the largest of all forcemains operated by the RDN. A section near Meadow Lane Road, Kite Way, and Planta Road is corroded and must be replaced.

How you can get involved

To stay informed of project updates, please:

  • Register by clicking the "subscribe" tab on the right-hand side of the page. By registering you will be kept up-to-date with progress on this project through our electronic communication.
  • Check out the Project Map.
  • Explore this webpage to find out more.
Consultation has concluded
  • April 1, 2022 Construction Update

    Share April 1, 2022 Construction Update on Facebook Share April 1, 2022 Construction Update on Twitter Share April 1, 2022 Construction Update on Linkedin Email April 1, 2022 Construction Update link

    The City of Nanaimo watermain works will be complete by April 8. Paving on Kite Way, Meadow Lane Road, and Hammond Bay Road may begin in the next week and is expected to be complete by April 14. The contractor will restore yards and boulevards through to the end of April. The RDN and City of Nanaimo thank all the residents for their cooperation and patience during this challenging project. We appreciate you!

  • December 16, 2021 Construction Update

    Share December 16, 2021 Construction Update on Facebook Share December 16, 2021 Construction Update on Twitter Share December 16, 2021 Construction Update on Linkedin Email December 16, 2021 Construction Update link

    The traffic lights on Hammond Bay Road at Chinook Road will be in place through January. Unanticipated conditions at this location required a temporary solution as we await arrival of the final materials needed to repair the forcemain in this area. Thank you for your patience as we complete the project and restore Hammond Bay Road as soon as possible.

    Watermain installation has started on Kite Way and will continue onto Meadow Lane Road. The Contractor will have a small crew working over the holidays and will recommence work with a full crew on Monday, January 3, 2022.

  • November 25, 2021 Construction Update

    Share November 25, 2021 Construction Update on Facebook Share November 25, 2021 Construction Update on Twitter Share November 25, 2021 Construction Update on Linkedin Email November 25, 2021 Construction Update link

    Construction of the forcemain upgrades is now substantially complete. The contractor is presently working on some final touch-ups in the excavation at Hammond Bay Road and Chinook Road, and backfilling the remainder of the excavations on Hammond Bay Road, Planta Road and Kite Way. Paving Hammond Bay Road and Planta Road is planned for December. Also in December, the contractor will begin the watermain work on Meadow Lane Road and Kite Way.

  • Night Work Notice - Meadow Lane Road

    Share Night Work Notice - Meadow Lane Road on Facebook Share Night Work Notice - Meadow Lane Road on Twitter Share Night Work Notice - Meadow Lane Road on Linkedin Email Night Work Notice - Meadow Lane Road link

    Night work will take place on the right-of-way at the south end of Meadow Lane Road on Friday, October 8 starting at 2 a.m. This night work is necessary to connect the new forcemain during low flow.

  • October 4, 2021 Construction Update

    Share October 4, 2021 Construction Update on Facebook Share October 4, 2021 Construction Update on Twitter Share October 4, 2021 Construction Update on Linkedin Email October 4, 2021 Construction Update link

    Forcemain installation on Meadow Lane Road and Kite Way is completing with a tie-in off of Meadow Lane Road in the early hours of October 5. A section of decommissioned forcemain on the right-of-way at the end of Meadow Lane Road will be removed in mid-October.

    Lining work will be performed throughout October to the end of November in the green-line section of the Project Map. Other important notes about the lining work include:

    • Single-lane traffic on Hammond Bay Road between Planta Road and Chinook Road.
    • 24-hour work to monitor curing from mid-October to end of October. You may see construction lighting and hear some noise from generators and vehicles.

    Watermain upgrades will commence in December on Meadow Lane Road and Kite Way.

  • July 16, 2021 Construction Update

    Share July 16, 2021 Construction Update on Facebook Share July 16, 2021 Construction Update on Twitter Share July 16, 2021 Construction Update on Linkedin Email July 16, 2021 Construction Update link

    Tree Clearing within the pipeline right-of-way off Meadow Lane is scheduled to start Monday, July 19, 2021. This is the start of the construction activity, followed by the delivery of piping material for the project. Excavation and pipeline installation is scheduled to start Monday, July 26, 2021 once the materials are delivered.

  • Construction Contract Awarded

    Share Construction Contract Awarded on Facebook Share Construction Contract Awarded on Twitter Share Construction Contract Awarded on Linkedin Email Construction Contract Awarded link

    At the RDN Regular Board Meeting on June 8, 2021, the RDN Board awarded the construction contract to Windley Contracting Ltd. for $5,505,380. Construction will proceed from late July 2021 to December 2021.