October 4, 2021 Construction Update

Forcemain installation on Meadow Lane Road and Kite Way is completing with a tie-in off of Meadow Lane Road in the early hours of October 5. A section of decommissioned forcemain on the right-of-way at the end of Meadow Lane Road will be removed in mid-October.

Lining work will be performed throughout October to the end of November in the green-line section of the Project Map. Other important notes about the lining work include:

  • Single-lane traffic on Hammond Bay Road between Planta Road and Chinook Road.
  • 24-hour work to monitor curing from mid-October to end of October. You may see construction lighting and hear some noise from generators and vehicles.

Watermain upgrades will commence in December on Meadow Lane Road and Kite Way.

Share October 4, 2021 Construction Update on Facebook Share October 4, 2021 Construction Update on Twitter Share October 4, 2021 Construction Update on Linkedin Email October 4, 2021 Construction Update link

Consultation has concluded