November 25, 2021 Construction Update
Construction of the forcemain upgrades is now substantially complete. The contractor is presently working on some final touch-ups in the excavation at Hammond Bay Road and Chinook Road, and backfilling the remainder of the excavations on Hammond Bay Road, Planta Road and Kite Way. Paving Hammond Bay Road and Planta Road is planned for December. Also in December, the contractor will begin the watermain work on Meadow Lane Road and Kite Way.