Nanoose Sewer Upgrades - Phase 1
The Nanoose sewer system delivers residential wastewater from the Fairwinds Development to the Nanoose Bay Pollution Control Centre. The forcemain and pump stations, constructed by the subdivision developer in the late 1980s, have a history of failures and require replacement. This will be done with a phased approach.
How you can get involved:
To stay informed of project updates, please subscribe and follow this project to receive occasional email updates.
The Nanoose sewer system delivers residential wastewater from the Fairwinds Development to the Nanoose Bay Pollution Control Centre. The forcemain and pump stations, constructed by the subdivision developer in the late 1980s, have a history of failures and require replacement. This will be done with a phased approach.
How you can get involved:
To stay informed of project updates, please subscribe and follow this project to receive occasional email updates.
-
Construction Complete on Nanoose Bay Pumpstation #6
Share Construction Complete on Nanoose Bay Pumpstation #6 on Facebook Share Construction Complete on Nanoose Bay Pumpstation #6 on Twitter Share Construction Complete on Nanoose Bay Pumpstation #6 on Linkedin Email Construction Complete on Nanoose Bay Pumpstation #6 linkConstruction on Nanoose Bay Pumpstation #6, at the end of Schooner Cove Drive, is complete. Detours have been removed and the area is ready for normal use. Thank you for your patience throughout construction. Construction remains ongoing on Nanoose Bay Pumpstation #5.
-
Phase 1 Construction Update
Share Phase 1 Construction Update on Facebook Share Phase 1 Construction Update on Twitter Share Phase 1 Construction Update on Linkedin Email Phase 1 Construction Update linkConstruction on Nanoose Bay Pumpstation #5, next to Fairwinds Landing on Dolphin Drive, is well underway. Completion is scheduled for the end of April 2024.
Construction on Nanoose Bay Pumpstation #6, at the end of Schooner Cove Drive, is also underway. Work is expected to be complete by the end of May 2024.
-
Trail Detour
Share Trail Detour on Facebook Share Trail Detour on Twitter Share Trail Detour on Linkedin Email Trail Detour linkThe area at the end of Schooner Drive is an active construction site. Please continue to observe and adhere to all construction signage.
The access road between the end of Schooner Cove Drive and the Nanoose Bay Pollution Control Centre will remain closed until the end of February 2024. Pedestrians should use the detour shown here to access the trail network.
-
Phase 1 Construction Update
Share Phase 1 Construction Update on Facebook Share Phase 1 Construction Update on Twitter Share Phase 1 Construction Update on Linkedin Email Phase 1 Construction Update linkConstruction on Nanoose Pumpstation #5 is expected to be completed in February 2024. Construction on Nanoose Pumpstation #6 is scheduled to start in January 2024.
-
Phase 1 Construction Update
Share Phase 1 Construction Update on Facebook Share Phase 1 Construction Update on Twitter Share Phase 1 Construction Update on Linkedin Email Phase 1 Construction Update linkNanoose Pumpstation #5 on Dolphin Drive is in the final stages of construction and is expected to be completed by the end of October 2023.
Construction of Nanoose Pumpstation #6 at the top of Schooner Cove Drive has been tendered and is expected to be completed in late Spring 2024.
-
Phase 1 Construction Update
Share Phase 1 Construction Update on Facebook Share Phase 1 Construction Update on Twitter Share Phase 1 Construction Update on Linkedin Email Phase 1 Construction Update linkThe delivery of electrical and controls equipment for Pumpstation #5 is delayed until July 2023. Construction crews will be back on site in June 2023.
-
Phase 1 Construction Contract Awarded
Share Phase 1 Construction Contract Awarded on Facebook Share Phase 1 Construction Contract Awarded on Twitter Share Phase 1 Construction Contract Awarded on Linkedin Email Phase 1 Construction Contract Awarded linkThe construction contract for Nanoose Pumpstation #5 and Forcemain has been awarded to Milestone Equipment Contracting Inc. This pumpstation is located on Dolphin drive, across the road from the Fairwinds marina. Construction is scheduled to start in late April 2022 and be completed in the Fall of 2022.
-
RDN Grant Fund Application Unsuccessful
Share RDN Grant Fund Application Unsuccessful on Facebook Share RDN Grant Fund Application Unsuccessful on Twitter Share RDN Grant Fund Application Unsuccessful on Linkedin Email RDN Grant Fund Application Unsuccessful linkThe RDN's grant application was unsuccessful. The project team is currently preparing the construction tender for Phase 1. Construction is scheduled for summer 2022
-
RDN Applied for $2 Million in Grant Funds
Share RDN Applied for $2 Million in Grant Funds on Facebook Share RDN Applied for $2 Million in Grant Funds on Twitter Share RDN Applied for $2 Million in Grant Funds on Linkedin Email RDN Applied for $2 Million in Grant Funds linkIn fall 2020, the RDN applied to the Investing in Canada Infrastructure Program for $2 million in grant funds to complete Phase 1 and replace high priority sections of the interceptor and upgrade select pump stations to meet new Work Safe access regulations and Electrical Codes.
Timeline
-
Forcemain Hydraulic Study and Phase 1 Engineering Design
Nanoose Sewer Upgrades - Phase 1 has finished this stage2020
-
Tenders
Nanoose Sewer Upgrades - Phase 1 has finished this stage2021 to 2022
-
Construction
Nanoose Sewer Upgrades - Phase 1 has finished this stagePumpstation #6: January 2024 to May 2024
-
Construction
Nanoose Sewer Upgrades - Phase 1 is currently at this stagePumpstation #5: ongoing